SZ Controller specifications

Manually decommission a SZ Controller

Performing these manual steps resets the SZ Controller and the non-volatile memory within the Ethernet Isolation Ports to the decommissioned state.

  1. Unplug the primary and secondary Ethernet Isolation Ports from the carrier.
  2. Remove both SZ controllers from the carrier and install them in the opposite slots: move the SZ controller in the right slot to the left slot and the SZ controller in the left slot to the right slot.
  3. Wait one or two minutes for the SZ to come up.
  4. Plug the primary and secondary Ethernet Isolation Ports into their original locations.
    Note

    This procedure can be useful in the rare case that a new database was brought online before the SZ controller was decommissioned.