The installation sequence described in this topic is only a
recommendation. You can perform these steps in the order that best meets the
needs of your project.
- Install vertical DIN rails
- Snap a SZ Controller Carrier
on the DIN rail.
- Snap the CHARMs Smart Logic
Solver (CSLS) Carrier onto the DIN rail
- Connect and install up to
eight baseplates under the CSLS Carrier on the DIN rail. Be sure to install
Separation Walls on I.S. Baseplates.
- Install the column
terminator to the last CHARM Baseplate
- Install the DIN Rail Stop
after the column terminator to prevent the baseplates from slipping down on the
DIN rail
- Wire the devices to the
terminal blocks and perform field wiring checkout
- Connect the bulk power
supplies to the CSLS Carrier
- Install the SZ Controllers
onto the carrier and provide power to the controllers
- Install the CHARMs Smart
Logic Solvers and Power Modules onto the CSLS Carrier
- Install the LS CHARMs
- Connect the SZ Controllers
to the DeltaV Area Control Network and to the Local Safety Network
- Connect CSLS to the Local
Safety Network