AGITATE phase logic configuration

Test the AGITATE running logic

Verify the running logic by modifying the AGITATE_TIME parameter and then manually running the AGITATE phase for UM_BLEND_500.

  1. Open the Batch display in DeltaV Operate.
  2. Click UM_BLEND_500 to open the unit module faceplate.
  3. Load the AGITATE phase.
  4. Click the AGITATE_TIME parameter data link and enter a value of 20.
  5. Open the faceplate for the AGITATE phase and the command list.
  6. Send a Start command.
  7. Go to the Process display.
  8. When the phase goes to complete, send a Reset command to return the phase to the Idle state.
  9. Unload the phase.
Note

After testing, the phase must be reset to the Idle state before it can be unloaded. It must then be unloaded so that it will be available later for Batch Executive control.